The grid by control region

Peak electricity demand in each of the grid's control regions, and where the national plan asks for new capacity to 2039.

52,302 MWpeak demand on the national grid (SIN), 2024May 2024, 17:00Source: Secretaría de Energía (SENER), Plan de Desarrollo del Sector Eléctrico 2025–2039 (PLADESE), Diario Oficial de la Federación, 17 October 2025, tables A1.5, A1.6 and 4.1 to 4.8, with CENACE data; read 5 November 2026
90,543 MWinstalled generating capacity, all Mexico, December 2024: nameplate, not available capacity; set against peak demand it does not measure headroom2024
4,358 MWthe three isolated systems' own peaks, added together: Baja California, Baja California Sur and Mulegé2024

Baja California, Baja California Sur and Mulegé run as systems isolated from the national grid: a plant there cannot draw on the rest of Mexico’s grid. Peak demand is in megawatts (MWh/h in the source: energy drawn in the busiest hour).

The grid's control regions

Each state in the colour of the CENACE control region that serves most of it; the boundaries follow the grid, not state lines

Noreste (northeast)Occidental (west)Oriental (east)CentralNoroeste (northwest)Norte (north)Peninsular (Yucatán Peninsula)Baja California (isolated)Baja California Sur (isolated)

Seven regions make up the national grid, and three systems in the Baja California peninsula stand apart. Coahuila is split: La Laguna is served by the Norte region, the rest by the Noreste; Mulegé is the northern part of Baja California Sur.

Source: CENACE's control regions as named in Secretaría de Energía (SENER), Plan de Desarrollo del Sector Eléctrico 2025–2039 (PLADESE), Diario Oficial de la Federación, 17 October 2025, tables A1.5, A1.6 and 4.1 to 4.8, with CENACE data; read 5 November 2026; which state falls where is our reading of CENACE's regional map.

Every region, ranked by its own peak

Peak demand by control region, 2024, MW: each region's own busiest hour (not coincident), with what it drew at the national peak hour

Each region peaks at its own hour, so the seven national-grid peaks add to 55,243 MW, more than the 52,302 MW the national grid drew at its single busiest hour. The Peninsular grew fastest in 2024 (10.1%).

Source: Secretaría de Energía (SENER), Plan de Desarrollo del Sector Eléctrico 2025–2039 (PLADESE), Diario Oficial de la Federación, 17 October 2025, tables A1.5, A1.6 and 4.1 to 4.8, with CENACE data; read 5 November 2026; the sum is our arithmetic.

How much each region's peak grew, 2010 to 2024

Change in peak demand from 2010 to 2024, percent

The Peninsular's peak nearly doubled (from 1,520 to 2,969 MW); the Central's is lower than in 2010. The national grid's rose from 35,310 to 52,302 MW.

Source: Secretaría de Energía (SENER), Plan de Desarrollo del Sector Eléctrico 2025–2039 (PLADESE), Diario Oficial de la Federación, 17 October 2025, tables A1.5, A1.6 and 4.1 to 4.8, with CENACE data; read 5 November 2026; changes are our arithmetic.

Where the plan wants new capacity, 2025 to 2039

Capacity the plan requires to be added by control region, 2025 to 2039, MW, all technologies (batteries included), additions only, replacements left out; Baja California includes Baja California Sur and Mulegé

The plan calls for about 76,000 MW of additions and 1,800 MW of replacements; the Noreste takes about 30%. A requirement in the plan is not a plant built: these are the volumes the state asks for, by year of entry, not projects under way.

Source: Secretaría de Energía (SENER), Plan de Desarrollo del Sector Eléctrico 2025–2039 (PLADESE), Diario Oficial de la Federación, 17 October 2025, tables A1.5, A1.6 and 4.1 to 4.8, with CENACE data; read 5 November 2026; the totals by region are our sums of each table.

What is absent, and why: installed capacity by region. The plan publishes installed capacity only for the whole country, by technology, so no regional capacity, reserve margin or headroom is drawn here. Nor are substation and transmission limits at a given site: a region that is growing, or one with capacity on the way, does not mean a new plant will be connected on time. That is checked site by site with CENACE and the CFE.

Related on this site Power and gasCompare the statesConsulting: where to locate

Deciding on these figures

We read the figures for your case, your product and your states, in writing first.

How we work

More data All the chartsThe comparison tableGrowth and outputPrices and the policy rateBanxico's rate since 2008The pesoExports and importsExports by stateWho buys from Mexico, and whatPorts and sea cargoHours to the border by roadTrucks entering the USA by portForeign investmentInvestment by stateForeign investment by type, country and sectorForeign investment: every country and sectorJobsWages and payroll taxSecurity by stateCargo theft by stateFactory wages and productivityEngineering and technical graduates by statePower and gasRemittancesThe release calendar